Huishan Economic Development Zone (HEDZ) was first established in July 2001 and approved by Jiangsu Provincial People’s Government as the provincial-level economic development zone in February 2002.Located in the due north of Wuxi, HEDZ is adjacent to Jiangyin — the county-level city of Wuxi with Shanghai-Nanjing Expressway, Wuxi-Jiangyin Expressway and Wuxi-Yixing Expressway meeting here, thus making it easily accessible.

What's on

1.Industry Promotion Project
SAIC Restructuring Soyat Project
Start the transformation of the whole plant in April. Complete the equipment installation before August. Finish the construction of plant road or special production base road and ensure to put it in service, by the end of December

China Recourses Infusion Restructuring Project
Finish the design, the relevant approval procedures and the equipment purchasing and transformation in the first half year. Start the engineering construction and equipment installation in July. Test the trial before the end of the year.

Blade Factory Project
Complete the project of civil engineering by the end of May. Start the installation of equipment installation in June. Finish the main move of the plant by the end of December.

Weifu High-tech Project
Complete the installation and adjustment of equipment in the first half year. Start the full operation in the second half.

Major construction, expansion or technical transformation projects
Focus on the follow up the project of FAW (First Auto Work) foundry technological transformation. Strive to start 51 super-million project in the whole year, including 39 super-100 million items.
 

2. Technology Innovation Project
L-Park
To achieve the output reaching 500 million RMB, registered foreign capital reaching 12 million U.S. dollars. To introduce more than 20 new joint ventures, 2 key professional projects (including National, Provincial Laboratories, Academicians, Dr. Workstations, and Brand Industry) into the park. To realize the introduction of medical, electronic equipment manufacturing enterprises achieving 3-5, and the "530" Projects achieving 5.
Complete the second phase construction of Public Instrument Platform, the amount of investment achieving 15 million RMB. Start the first phase construction of the 1000㎡pilot test platform. Introduced or co-create to establish one life science venture capital management company, importing five intermediaries
Completed C-Zone first phase construction of 41,000 ㎡. Open the park in August. Start second phase construction for C-Zone. Finish the removal and formation of D,E-zone. Start the construction of 250 acres for D-Zone.
O-Park
To realize an annual output of 500 million RMB, paid-in foreign capital 10 million U.S. dollars; to introduce 30 enterprises of Software Outsourcing Service and Digital Interactive Entertainment.
To create game developing technology, software testing and offshore outsourcing technical support platform and fully complete in the first half.
To ensure that buildings under construction achieving 185,000 m2 in the year 2010; fully complete Digital Harbor and put into trial operation by the end of the year; complete O-Par Perceived Age Hotel and put into trial operation in the first half year; complete Convention Center and put into trail operation before September; fully complete Creative Park and put into use; finish the construction of colorful Headquarters Building during the year; fully complete 4 roads in the park during the first half of the year; complete the landscape engineering in March; finish the listing of 15 acres commercial land in the first half of the year.
D-Park
Ensure that the introduction of digital information related companies reaching 20; to achieve annual billing income 5 billion and paid-in registered foreign capital $ 3,000,000.
To accelerate Huishan network technology transformation and the construction of demonstration area, which is co-operated by Tsinghua University, Shenzhen Institute and Wuxi Guolian Group Put the first phase construction into use in June.
Ensure that building construction amount to 153,000 m2; fully complete the Research and Development Building, General Service Building (high apartment) during the year; complete 50% of the Tsinghua University Innovation Centre (Incubator Building) Project; realize the North River landscape construction project in the first half; complete the road and pipeline network (including electricity) construction by the end of August.
W-Park
To achieve the full operation of Tianqi components project in April 2010. Complete the overall machine construction for Aerospace Wanyuan Project before the end of July; put Riel Bamboo Wind Project into operation in August 2010.
Complete the continuing construction projects and landscape of key area project, including the construction of business platform and hotel, road, water conservancy, entrance landscape; complete the 5 new outdoor projects, including the terminal building, standard factory building, construction of testing platform, the green landscape along the Road. Ensure that the park could b e opened in May.